A lift plan is the written answer to four questions: how heavy, how far, how high, and what is in the way. Here is where Canadian rules require one, and what a supplier needs from you to plan the lift.
Not a lift plan
This guide explains what a lift plan covers and where the rules require one. The plan itself is made for the actual truck, its load chart and the site, by the competent people your province requires, with an engineer where the rules or the ground call for one. Never use a page or a calculator to decide that a lift is safe.
R 03 mWhat a lift plan is for
A boom truck's capacity is not one number. It changes with radius, boom length, the quadrant the load is in and how the outriggers are set, which is why Alberta's s.63(1) requires the truck to carry load charts showing rated capacity at all permitted boom angles and radii1. A lift plan pins the job to one place on that chart.
At its simplest, the plan is the operator's check before each lift. It becomes a document when the lift is heavy, near a line, over people or shared between cranes. Either way it answers the same questions:
| Question | What the plan records | Why it matters |
|---|---|---|
| How heavy? | The load plus hook block, slings and shackles | A hoist's rated load does not allow for the rigging2 |
| How far? | Radius at the pick and at the set; the larger one governs | Capacity falls as radius grows |
| How high? | Landing height, plus load, rigging and clearance | Sets the boom length and angle |
| Where does it stand? | Set-up position, outrigger spread, ground and pads | Chart ratings assume full extension and firm, level ground2 |
| What is in the way? | Power lines, buildings, other cranes, people below | Alberta requires collision procedures between lifting devices, and loads kept off workers where practicable1 |
| Who does what? | Operator, rigger, signaller, person in charge | Signals, and who may stop the lift |
Under Alberta's s.64, only a competent worker authorized by the employer may run a lifting device, and that worker must on request show knowledge of load charts and the hoisting signal code1.
R 06 mWhen Alberta requires a lift calculation
Alberta's rule is one sentence: the employer must ensure a lift calculation is completed for any lift exceeding 75% of a crane's rated capacity1. Two points of reading:
- Which machines. Section 68.1 says "crane", the Code's broad word for equipment designed to lift, lower and move loads horizontally1. It does not say "mobile crane", which the Code defines as a crane other than a boom truck and which s.88 uses to adopt CAN/CSA Z150-981. Plan on the basis that it reaches a boom truck lift, and check your employer's procedures.
- Rated capacity where. The figure that counts is the chart capacity at the lift's radius and configuration, not the truck's headline rating.
The Code does not say what the calculation contains. A useful one records the load and rigging weight, the radius at pick and set, the configuration (boom length, outriggers, quadrant), the chart capacity there, any deductions, and the percentage of the chart used.
Example: two provinces, one lift
Example inputs, not from a real chart: a 1,800 kg load with 120 kg of rigging, so 1,920 kg on the hook, set at 12 m on a truck whose chart gives 2,400 kg at 12 m over the rear, with a 20 m maximum permitted radius.
- 1,920 ÷ 2,400 = 80% of the chart. In Alberta that is over 75%, so a lift calculation is required.
- In BC, 80% is under the 90% critical-lift line, so it is not a critical lift on that test.
- If the chart gave 2,100 kg at 12 m, the lift would use about 91% at a radius more than half of 20 m: a critical lift in BC.
R 09 mBC's critical lifts
BC defines a critical lift, then requires a written plan for it. For boom trucks, the definition includes a lift over 90% of rated capacity at a load radius more than 50% of the maximum permitted radius, and any lift over or between energized high-voltage conductors3. The full list also covers3:
- a tandem lift with any one crane over 75% of its rated capacity, or more than two cranes;
- lifting a person in a work platform attached to a crane;
- a load whose centre of gravity, or a sling leg's length, changes during the lift;
- a lift from a floating base over 90% of rated capacity, and lifting a submerged load.
For every critical lift, a written plan must be at the site during the lift. It covers rigging details, wind speed limits, maximum hoist line speed, maximum travel speed where it applies, load distribution, and whether signallers are needed and where they stand. Immediately before the lift, a pre-job meeting goes through the plan with everyone involved; the supervisor documents it, and it is repeated whenever the people or the equipment change3.
Two more BC rules feed the plan. A boom truck rated 10 tonnes (11 tons) or more needs a load weight indicator or a system that stops it lifting beyond rated capacity3. And a boom angle indicator, plus a radius or boom extension indicator, is required wherever rated capacity depends on those values3.
R 12 mKnowing the weight of the load
Every margin in a lift plan is a percentage of a weight. BC requires the weight of each load to be determined and communicated to the operator and the rigger; where it cannot be determined accurately, the crane needs a load weight indicator or an overload prevention system3. Alberta makes the employer give the operator, the rigger and the person in charge of the lift the information they need to determine it1.
Count everything below the boom tip. IHSA notes that a hoist's rated load does not allow for hook blocks, hooks, slings or equalizer beams, so their weight is added to the load2.
Where the weight comes from
- The bill of lading, delivery slip or packing list.
- The manufacturer's data plate or drawing, for units such as rooftop equipment, tanks and transformers.
- Shop or engineering drawings, for precast, steel and trusses.
- For bundles, the count times the unit weight.
- A weigh scale, when nothing else is reliable.
Ask what is inside. A tank with liquid in it weighs more than its empty weight, and a load whose centre of gravity moves during the lift is a critical lift in BC3.
R 15 mMargins and duty cycles
The chart is a limit, not a target. IHSA recommends choosing a crane with at least a 5% working margin over the capacity each lift needs2. For duty-cycle work such as placing concrete, manufacturers typically require chart ratings to be reduced, usually by 20%, or supply a separate chart2.
Example, from the lift above: 1,920 kg plus a 5% margin needs at least 2,016 kg of chart capacity at the radius. On repetitive bucket work, the 20% reduction raises that to about 2,520 kg.
Three things eat the margin before the lift starts:
- Radius error. Boom angle indicators can be off by as much as 2° and should not be relied on for critical lifts; a measured radius is better2. Radius also grows under load as the boom deflects2.
- Out of level. In IHSA's example for one crane, 1° out of level cost 10% of chart capacity with a short boom and 30% with a long one2.
- The quadrant. Capacity is normally greatest over the rear, less over the side, and may be nil over the front2.
The boom truck size estimator applies the margin and the duty-cycle reduction to your numbers. More in how to read a load chart.
R 18 mPower lines and signallers
An overhead line within reach of the boom adds people as well as distances to the plan:
- Alberta. Within 7 m of a line, the employer must determine the voltage and set the limit of approach before work1.
- British Columbia. A lift over or between energized high-voltage conductors is a critical lift, like a lift over 90% of capacity at long radius3. If the distance cannot be kept, the owner's written assurance is required; where the lines cannot be isolated, rerouted or guarded, a safety watcher with a positive stop signal is designated4.
- Ontario. Where a crane could encroach, the constructor sets written procedures5, and a competent worker is designated as signaller, in full view of the operator and with a clear view of the conductor5.
- Manitoba. Within 3 m of a line, the employer notifies the electrical authority, gets written instructions and, when instructed, assigns a signal person6.
- Newfoundland and Labrador. The voltage and clearance come in writing from the utility; without them, 5.5 m must be kept7.
Signals matter away from lines too. In BC, an operator who cannot see the boom, load line, hook and load through the whole lift acts only on the directions of a qualified signaller who can, and must stop on a stop signal from anyone3. Distances by province are in how close a boom truck may work to a power line.
R 21 mWho signs off
No single rule names one signature. The duties are spread out, and the plan says who holds each:
| Who | Duty | Where |
|---|---|---|
| Employer | Makes sure a lift calculation is done above 75% of rated capacity and, under s.64, that only a competent, authorized worker operates | Alberta1 |
| Operator | Does not move a load while in doubt about the safety of workers nearby; stops on anyone's stop signal | Alberta1; BC3 |
| Supervisor | Documents the pre-job meeting for a critical lift | BC3 |
| Qualified person | Chooses where a boom truck sets up next to an excavation, slope or backfill | BC3 |
| Constructor | Sets written procedures where a crane could encroach on a power line; is consulted on ground conditions and the set-up location | Ontario58 |
| Engineer or manufacturer | Determines rated capacity under CSA Z150-16 or Z150.3-17 | Ontario5 |
For heavy lifts, a non-Canadian reference sets a ground trigger: Queensland's code calls for geotechnical certification before lifts such as bridge beams of 10 t or more, or loads of 50 t or more9. See outriggers and ground bearing pressure.
On an operated rental the operator comes with the truck, while the site belongs to the customer's employer or constructor. Settle in writing, before the day, who prepares the plan, who supplies the weight and the ground information, and who is in charge of the lift. And respect the stop: an operator who will not lift while in doubt is doing what Alberta's Code requires1.
R 24 mWhat to give a supplier so they can plan the lift
A supplier quotes the job, and the quote is only as good as the brief. The quote request on BoomTrucks.ca asks for what a lift plan needs:
| Field | What to enter |
|---|---|
| Weight of the load, kg | The heaviest piece and where the figure came from; the rigging too, if you know it |
| Radius, m | Horizontal distance from where the truck can stand to the pick or the set, whichever is farther |
| Height, m | The landing height above the ground the truck stands on |
| What is lifted, from where to where | Item, size, pick point, landing and number of lifts |
| How long | From one lift to over a month |
| Ground where the truck sets up | Paved, gravel, soil or grass, soft or frozen, or don't know |
| Power lines within about 7 m | Yes, no or don't know |
| Operator | With an operator, bare with your own certified operator, or not sure |
In the notes, add access and overhead clearance for the truck, the set-up space and its distance from edges, whether the load passes over people, site hours, and who will direct the lift.
Request a quote; it only goes to a company with your consent. With your consent, your request goes to one company that rents, sells or finances boom trucks in your area. That company may pay BoomTrucks.ca for the referral. Start with the quote request, or size the lift first with the size estimator.
Questions people ask
What is a critical lift for a boom truck?
How do I find the weight of a load for a crane lift?
From the delivery slip, the manufacturer's plate or drawing, or a weigh scale. Then add the hook block, slings and shackles: IHSA notes a hoist's rated load does not allow for them2. In BC, if the weight cannot be determined accurately, the crane needs a load weight indicator or an overload prevention system3.
Who is responsible for a boom truck lift plan?
When does a boom truck need a signaller?
In BC, whenever the operator cannot see the boom, load line, hook and load through the whole lift3. In Ontario, a designated signaller is required where a crane could encroach on a power line5, and in Manitoba a signal person is assigned within 3 m of a line when the electrical authority instructs it6.
Sources
- Occupational Health and Safety Code, Alberta Regulation 191/2021 (office consolidation)Alberta King's Printer (Government of Alberta) · Consolidation current as of 2025-03-31 (amendments to AR 210/2024); verified 2026-10-05
- Hoisting and Rigging Safety Manual (M035)Infrastructure Health & Safety Association (Ontario) · January 2020 printing; verified 2026-10-05
- OHS Regulation Part 14: Cranes and HoistsWorkSafeBC · Online regulation incl. B.C. Reg. 176/2024 (eff. 2024-10-01); verified 2026-10-05
- OHS Regulation Part 19: Electrical SafetyWorkSafeBC · Online regulation incl. B.C. Reg. 223/2022 (eff. 2023-03-01); verified 2026-10-05
- O. Reg. 213/91: Construction Projects (Occupational Health and Safety Act)Government of Ontario (e-Laws) · Consolidation period from 2026-04-20 (last amendment O. Reg. 116/26); verified 2026-10-05
- Workplace Safety and Health Regulation, M.R. 217/2006Government of Manitoba (Manitoba Laws) · Consolidation current 2026-09-01 to 2026-10-01 (last amendment M.R. 19/2026); verified 2026-10-05
- Occupational Health and Safety Regulations, 2012 (NLR 5/12)House of Assembly of Newfoundland and Labrador · Consolidated text (currency date not captured); verified 2026-10-05
- Technical guideline on requirements for cranes at construction projectsOntario Ministry of Labour, Immigration, Training and Skills Development · published 2024-01-02, updated 2024-01-04; verified 2026-10-05
- Mobile crane Code of Practice 2024Workplace Health and Safety Queensland (State of Queensland) · code commenced 2024-09-23; verified 2026-10-05
Related
- G-401 Operator certification by province Thresholds, certificates and issuers in every province and territory we researched, from Alberta's boom truck trade to Ontario's MCO 1 and 2.
- G-402 Inspection rules Annual engineer inspections, two-year NDT cycles, Ontario's crane log and which CSA edition each province adopts.
- G-403 Power-line clearance The limits of approach side by side, the Alberta 7 m trigger, BC safety watchers and Ontario signallers.